Estimate accuracy

leave a comment »

1. Rough Order of Magnitude (ROM) Estimate: made during project initiating, -25% –> +75% (depend on how much is known about the project)

2. Budget Estimate: made during project planning, -10% –> +25%.

3. Definitive Estimate: as the project progress, the estimate becomes more refined. Can be 2 cases:

– Case 1: -10% –> +10%.

– Case 2: -5% –> +10%.